Week 4-5 Progress Update

This week we accomplished a lot.  During lab, we permanently affixed the chassis of the submersible together with PVC glue.  We also worked on making brackets to mount the motors with.  During our post lab meet up, we continued working on the brackets to mount the motors with.  We finished most of the brackets and successfully mounted one of the motors to the chassis.  We also drilled all of the holes in the chassis where the other motors will be mounted.  Additionally, we got the camera that we ordered from Cabela's in the mail on Tuesday evening.  We also ordered the wire for our tether and are expecting it in the mail next week.  Our goal for the upcoming week is to finish mounting the motors and check out the camera that came in the mail.